Risk assessment of river-type hydropower plants using fuzzy logic approach

dc.contributor.authorKüçükali, Serhat
dc.contributor.authorID20413tr_TR
dc.date.accessioned2016-08-11T13:24:43Z
dc.date.available2016-08-11T13:24:43Z
dc.date.issued2011
dc.departmentÇankaya Üniversitesi, Mühendislik Fakültesi, İnşaat Mühendisliği Bölümüen_US
dc.description.abstractIn this paper, a fuzzy rating tool was developed for river-type hydropower plant projects, and risk assessment and expert judgments were utilized instead of probabilistic reasoning. The methodology is a multi-criteria decision analysis, which provides a flexible and easily understood way to analyze project risks. The external risks, which are partly under the control of companies, were considered in the model. A total of eleven classes of risk factors were determined based on the expert interviews, field studies and literature review as follows: site geology, land use, environmental issues, grid connection, social acceptance, macroeconomic, natural hazards, change of laws and regulations, terrorism, access to infrastructure and revenue. The relative importance of risk factors was determined from the survey results. The survey was conducted with the experts that have experience in the construction of river-type hydropower schemes. The survey results revealed that the site geology and environmental issues were considered as the most important risks. The new risk assessment method enabled a Risk Index (R) value to be calculated, establishing a 4-grade evaluation system. The proposed risk analysis will give investors a more rational basis to make decisions and it can prevent cost and schedule overrunsen_US
dc.description.publishedMonth10
dc.identifier.citationKüçükali, S. (2011). Risk assessment of river-type hydropower plants using fuzzy logic approach. Energy Policy, 93(10), 6683-6688. http://dx.doi.org/10.1016/j.enpol.2011.06.067en_US
dc.identifier.doi10.1016/j.enpol.2011.06.067
dc.identifier.endpage6688en_US
dc.identifier.issn0301-4215
dc.identifier.issue10en_US
dc.identifier.startpage6683en_US
dc.identifier.urihttp://hdl.handle.net/20.500.12416/1224
dc.identifier.volume39en_US
dc.language.isoenen_US
dc.publisherElsevier Science Ltden_US
dc.relation.ispartofEnergy Policyen_US
dc.rightsinfo:eu-repo/semantics/closedAccessen_US
dc.subjectHydropoweren_US
dc.subjectRisk Analysisen_US
dc.subjectFuzzy Logicen_US
dc.titleRisk assessment of river-type hydropower plants using fuzzy logic approachtr_TR
dc.titleRisk Assessment of River-Type Hydropower Plants Using Fuzzy Logic Approachen_US
dc.typeArticleen_US
dspace.entity.typePublication

Files

License bundle

Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: